Windyhill Battery Storage Facility πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland /
Dates
First heard 2022-06-16
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Energy GridPower Ltd /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.929502+-4.372131
Coordinates
55.929502, -4.372131
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
1088 / 10596

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2023-07 report):

Plant Name / State
Windyhill Battery Storage Facility / scotland
Go live / estimated go live
/
MW
200
Status
planning
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 09/02/2022 ->

2024-01